Union Station

Construction update

Completed elements

  • VIA elements
    • Panorama Lounge
    • York West Teamway Catering Space
    • East Concourse office
    • Baggage handling system
    • Heritage washrooms
    • Office space
    • Great Hall Ticket offices
    • GO York Concourse
    • West Wing
    • Structural support column replacement
    • Electrical systems
    • Mechanical systems
    • Exterior heritage façade restoration (including the roof of the West and East wings and Centre Block)
    • Loading dock
    • Bay and York Teamways
    • Northwest PATH – Phase 1
    • Expanded bike station

What's to come?

  • Completion of Stage 1, which includes:
    • Base building of the retail concourse beneath the York and VIA Concourses. The space will then be turned over to the station's head lessee. Please visit torontounion.ca/eat-and-shop for updates on occupancy of the retail concourse.
    • Stage 2/3
      • Bay Concourse structures (now to Q3 2017)
      • Bay Concourse finishes (Q2 2017 to Q1 2018)
      • Moat covers (now to Q4 2017)
      • Great Hall restoration (now to Q4 2017)
      • VIA Concourse (now to Q4 2017)
      • Bay & York moat covers (Q2 to Q3 2018)

Estimated substantial completion of stage 2/3 construction is the end of 2018.


Back to: Union Station